A chain of assumptions and leaving it to subcontractors...TEPCO “We didn’t check it ourselves”...Why did the mistake happen when removing debris from Fukushima Daiichi?

Enterprise
0001@Old Man Friends Club ★.Sep. 6, 2024 (Fri) 14:48:38.10ID:Ih/NynDH9
On the 5th, Tokyo Electric Power Company (TEPCO) released the results of its investigation into the cause of the delay in the operation to collect trace amounts of melted nuclear fuel (debris) at the No. 2 reactor at the Fukushima Daiichi Nuclear Power Plant due to a mistake. The company said that workers rushed to make preparations under high radiation levels and failed to notice their mistake due to their assumptions. This exposed TEPCO’s attitude of leaving the work to subcontractors, with no TEPCO employees on site, and sloppy management that failed to detect mistakes during inspections. Tokyo Electric Power Company has indicated that it plans to begin sampling as early as next week, after taking measures to prevent recurrence. (Arai Mutsuyoshi, Yamashita Hazuki)
◆ “A chain of assumptions” and “leaving it to subcontractors”
The mistake was made in the pipe (approximately 1.5 meters long, 16 centimeters in diameter, and weighing approximately 95 kilograms) used to push the fishing rod-style device for collecting debris into the containment vessel. When working to connect five pipes with a cable, the first pipe was mistakenly connected to the fourth. According to TEPCO, all five cables are almost identical in appearance, but some have different specifications, such as whether or not they have screw holes, and if they are connected in the wrong order, they may not be able to be pushed in halfway. On July 27, workers inside the No. 2 reactor building carried a pipe to the front of the equipment. At that time, a pipe was left behind in the temporary storage area. When connecting on the 28th, they realized they were missing, so they connected as the fourth on the 29th. The pipe I forgot was the first one, but I thought it was the second one, so I decided it would be okay to connect it to the fourth one. A chain of assumptions began. The factors cited as contributing factors were high radiation levels at the site, which meant workers could not stay there for long, so they rushed the work, and they also did not check properly, so they did not notice the mistake and assumed that they were doing it correctly. The worker was wearing full-face masks and heavy protective clothing and overlooked the numbers on the pipes indicating the connection order. Furthermore, the person in charge at Mitsubishi Heavy Industries, the general contractor in charge of the site, falsely reported to TEPCO that “preparation was completed on the 28th.” TEPCO did not have any employees present at the site, and the order in which the pipes were connected was not included in the inspection items, so it did not check and therefore did not notice the mistake. TEPCO’s Akira Ono, head of decommissioning the plant, said, “Our foresight was lacking. “We need to give broader consideration to safety and reliability in the future,” he said in a remorseful statement. [Omitted]
◆ “TEPCO’s involvement was weak” Troubles and mistakes continue
According to TEPCO, about 5,000 people are involved in the decommissioning work at Fukushima Daiichi every day. Of these, approximately 1,000 are TEPCO employees. The core of the work on site is carried out by approximately 4,000 general contractors and subcontractors. TEPCO employees will mainly be checking the progress and dangers of the work. However, management of the work was lax, and troubles continued, including one in October last year when a worker at a multi-nuclide removal facility for contaminated water was doused in cleaning waste liquid and exposed to unexpected radiation. Continue reading in the Tokyo Shimbun, September 6, 2024, 6:00 a.m.

東京電力「自分たちで確認していない」…福島第1のデブリ取り出しでミス、どうして起きた?:東京新聞 TOKYO Web
東京電力福島第1原発2号機で溶け落ちた核燃料(デブリ)の微量を採取する作業がミスで延期された問題で、東京電力は5日、原因の調査結果を公...
0003Anonymous Donburako.Sep. 6, 2024 (Fri) 14:50:40.77ID:JlUU+H9k0(1/6)
Dismantle it.
0005Anonymous Donburako.Sep. 6, 2024 (Fri) 14:51:02.66ID:BSzSj4Dh0
A middleman.
0006Anonymous Donburako.Sep. 6, 2024 (Fri) 14:51:09.17ID:SfCUignw0
Stop it fatty.
0007Anonymous Donburako.Sep. 6, 2024 (Fri) 14:51:41.17ID:JlUU+H9k0(2/6)
The person in charge at Mitsubishi Heavy Industries is cutting corners and making false reports.
0020Anonymous Donburako.Sep. 6, 2024 (Fri) 14:57:20.83ID:k2Ub6ngR0
>>7
Since the client, TEPCO, received false reports, there’s nothing they can do
Since the client usually isn’t on-site
The general contractor, Mitsubishi, ultimately bears all responsibility
But the primary contractor was the one that actually led the work, so that was probably the right choice.
0008Anonymous Donburako.Sep. 6, 2024 (Fri) 14:51:59.72ID:1Kx2Ql1f0
The outcome would have been the same even if TEPCO had been there.
It would have been better if the ordering party or the person in charge had been there.
A commentator said earlier that if they had been on TV the mistake wouldn’t have happened, but I don’t think that’s true.
0009Anonymous Donburako.Sep. 6, 2024 (Fri) 14:52:28.05ID:JlUU+H9k0(3/6)
We’re working with the worst possible combination of people.
0010Anonymous Donburako.Sep. 6, 2024 (Fri) 14:53:08.44ID:rQO8hd0e0
It doesn’t matter because it’s never going to end.
0011Anonymous Donburako.Sep. 6, 2024 (Fri) 14:53:34.57ID:WoVVZ45P0
Next up is Niigata. I’m excited.
0013Anonymous Donburako.Sep. 6, 2024 (Fri) 14:53:56.66ID:wmoV0IBT0
The obstacles of assumptions are troublesome and even if you check them properly they slip through.
0014Anonymous Donburako.Sep. 6, 2024 (Fri) 14:54:16.87ID:wkXn24Br0
I’m a supporter of nuclear power, but I think TEPCO just can’t do it at all. They don’t have the capacity to operate a nuclear power plant.
0015Security Guard [lv.6] [Sprout].Sep. 6, 2024 (Fri) 14:54:45.98ID:U4CWFs180
All they had to do was write the number on the pipe, but all the characters are idiots.
0056Anonymous Donburako.Sep. 6, 2024 (Fri) 15:14:56.60ID:uBh+1p5a0
>>15
You overlooked the number that was written.
You make mistakes too lol.
0017Anonymous Donburako.Sep. 6, 2024 (Fri) 14:55:12.86ID:LjS9Ujg80
He has a tendency to just pass the buck.
0019Anonymous Donburako.Sep. 6, 2024 (Fri) 14:56:56.66ID:Z8vIqrPG0
That’s the reality of Japan. Passing the buck and cutting out the middleman.
0027Anonymous Donburako.Sep. 6, 2024 (Fri) 14:58:33.68ID:6Gju1U0L0(2/2)
>>19
We need to put a stop to the unlimited construction bills paid for with tax money

We have to make them pay for anything above the estimated cost out of their own pocket.

0021Anonymous Donburako.Sep. 6, 2024 (Fri) 14:57:44.62ID:xc5olm+c0
I’m not sure if they even have a responsible attitude towards cleaning up after themselves. It’s a serious matter, so they need to do multiple checks properly. It’s a mess like this even before the contents have been taken out, so it’s not surprising that anything could happen.
0022Anonymous Donburako.Sep. 6, 2024 (Fri) 14:57:47.06ID:edO038ZO0
TEPCO executives should become a suicide squad, grab pickaxes and go retrieve it lol.
0024Anonymous Donburako.Sep. 6, 2024 (Fri) 14:57:48.47ID:ZXBdu1sm0
Don’t run away just because you don’t want to get exposed to radiation. You don’t show your face on the job site, so the subcontractors don’t feel nervous.
0025Security Guard [lv.8] [Sprout].Sep. 6, 2024 (Fri) 14:57:50.90ID:KLVaUhWI0
It just seems like TEPCO.
0026Anonymous Donburako.Sep. 6, 2024 (Fri) 14:58:15.99ID:bpwf+4Pc0
Why not colour code it or something?
0028Anonymous Donburako.Sep. 6, 2024 (Fri) 14:59:14.12ID:+3z5Upw40
The dark side of TEPCO. TEPCO is not just about people working in the Uchisaiwaicho office. It’s a fact that the elite college graduates can’t accept.
0029Anonymous Donburako.Sep. 6, 2024 (Fri) 14:59:34.17ID:DHsCieDT0
It’s an easy job because you get a bonus for doing this.
0030Anonymous Donburako.Sep. 6, 2024 (Fri) 14:59:50.13ID:TnTxEBAw0
This is the Japanese aesthetic style, right?
0031Anonymous Donburako.Sep. 6, 2024 (Fri) 15:00:04.10ID:9nZbXQ9I0(1/2)
This is the corporate culture of today’s large companies.

Even in general contractors’ construction and plant work,
they leave it up to the subcontractors to do their own inspections,
and even leave the benchmarks (the xy axis base points that serve as the standard for buildings and equipment) to the contractors.
If corners are cut in places that will be hidden by the finishing work,
it can no longer be checked.
General contractors have always insisted on having the ability to do construction because they have been inspecting and checking,
but now they’re not doing so well.

0032Anonymous Donburako.Sep. 6, 2024 (Fri) 15:00:39.30ID:J6Ds5E8d0
TEPCO is still a company that shouldn’t be left in the hands of nuclear power plants.
0033Anonymous Donburako.Sep. 6, 2024 (Fri) 15:01:30.47ID:b+S2VA4y0
The Mitsubishi rep who made the false report is also shit.
0036Anonymous Donburako.Sep. 6, 2024 (Fri) 15:02:08.54ID:9nZbXQ9I0(2/2)
>>33
I don’t think even the Mitsubishi people checked it.
0034Anonymous Donburako.Sep. 6, 2024 (Fri) 15:01:38.54ID:zTwya7nf0
Are the actual workers part-time workers from the fifth level?
0039Anonymous Donburako.Sep. 6, 2024 (Fri) 15:03:39.30ID:Y8tqGeqD0(1/2)
It’s okay because it was just a case of the subcontractor being bad.
0041Anonymous Donburako.Sep. 6, 2024 (Fri) 15:03:57.33ID:JlUU+H9k0(6/6)
>>39
Are you stupid, TEPCO?
0040Anonymous Donburako.Sep. 6, 2024 (Fri) 15:03:49.83ID:1M1/Nirh0
What an incredible legacy to leave to our future generations. I don’t know if they’ll be Japanese or not.
0043Anonymous Donburako.Sep. 6, 2024 (Fri) 15:05:25.20ID:+Gg8wwtf0
Dangerous work is outsourced. As for funding, it’s not a problem as the government and the people will cover the costs.
0045Anonymous Donburako.Sep. 6, 2024 (Fri) 15:06:13.12ID:9HAgRwgy0
Subcontractors can’t be replaced so they don’t need to be successful
and to last a little longer, I’ll do this.
Reference: https://asahi.5ch.net/test/read.cgi/newsplus/1725601718